Roadmap & Milestones

Engine Evidence → Passenger Aircraft

A paced sequence that prioritizes data, safety, and certification. Each milestone unlocks the next—culminating in mid–long range passenger operations across multiple authorities.

Milestones & Deliverables

Dependencies and artifacts are explicit to keep the pace across engineering, certification, and operations.

M0

Architecture & Safety Plan

Down-select, supplier MoUs, HAZOP/FMEA v1, PRD & ventilation strategy, test rig approvals.

Depends
Outputs
Test authorization, baseline safety artifacts.
M1

Single-Sector: Cold-Flow + Ignition

Ignition mapping and flashback margins (unpressurized/low-pressure); DAQ and interlocks validated.

Depends
M0
Outputs
Ignition map v1, safety interlocks validated.
M2

Pressurized Hot-Fire

Single-sector hot-fire at pressure; NOx and stability maps across φ / load; initial geometry tuning.

Depends
M1
Outputs
NOx/stability map v1; geometry shortlist.
M3

Core-Engine H₂ Ground Run

Fuel metering, transients, surge margins; controls/health monitoring; engine-airframe trades.

Depends
M2
Outputs
Core run data pack; controls tuning notes.
M4

Flight Testbed Kick-off

DOA/ODA engagement, approvals, airframe integration plan; airport ops rehearsal.

Depends
M3
Outputs
Testbed plan & approvals; ops playbooks v1.
M5

Global Cert Mapping

Means-of-compliance drafts for EASA/FAA + partner authorities; artifact packaging and deltas.

Depends
M2–M4
Outputs
Authority-specific packs; audit trail v1.
M6

Airport Pilots

Refuel/turnaround rehearsals; PRD/ventilation validation; procedures, training & maintenance flows.

Depends
M4–M5
Outputs
Ops playbooks v2; partner sign-offs.
M7

Passenger Program Gate

Sizing for mid–long range aircraft; supply plan; international deployment sequencing.

Depends
M5–M6
Outputs
Go/No-Go; aircraft program launch.
Testbed and hydrogen systems

Risks & Mitigations

We continuously reduce technical and certification risk—with traceable artifacts.

Flashback / Stability
Pressurized maps; staged mixing; ignition control
Emissions
Lean-premix/micromix geometry tuning; NOx maps
Ground Ops
PRD, purge, ventilation, detection; playbooks
Evidence
Automated data capture; MoC drafts; audit trail

Engines first. Certification from day one.

Co-develop modules or host airport pilots to accelerate the path to mid–long range passenger service.